The Guardian -
13 Jul 2022 13:28

Firm's president at time of disaster among five defendants found liable for £80bn in damage by Tokyo court A court in Japan has ordered former executives of Tokyo Electric Power (Tepco) to pay ¥13tn (£80bn) in damages for failing to prevent a triple meltdown at the Fukushima Daiichi nuclear power plant in 2011. The ruling by Tokyo district court centred on whether senior Tepco management could have predicted a serious nuclear accident striking the facility after a powerful tsunami.